Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

GLAD

Things that have worked very well and made team very happy

SAD

Disappointments, things that has not worked as well as hoped

MAD

Things that didn't work well wasted a lot of time

good Good relationship building for the client

feedback from Farhan that progress is slow, GTP UI is slow, Recording is slow, and it is NOT related to the computer.

Issues aren't being resolved. we have partial successes and then issue re-appears.

Farhan is very patient and spending lots of time with usteam is working very hard(+1) (+2)

Don't have visibility on status of issues

Build doesn't have version number, having OnPremise<5>.rar looks unprofessional, looks like we don't have build process.

Team work on STC is great (+1)

Team is working very hard (+2)Start on Playwright (+1) (+2}

2x daily scrums stopped being effective.

Takes a long time to do manual operations on the machine -> need scripts or automation

Added ODBC for STC (+1)

Don't have a build creation process automated, can’t tell build version.

Glad that our team has been handling STC-related implementations and testing exceptionally well.

Ahmer can't pull code and create build on his local, means he is always stuck on dependency

Implemented JWT for SWBC

It's unfortunate that we can't test getting OTP via the database since we don't have valid credentials.

UI/UX Progress is good (+12)

Team is being patient enough to explain the QA ecosystem on the certain flow which i was sceptical about.

My hope was to have larger participants of our team to have more interaction so that the outcome would be better compared to what we have now, sharing the thought process would help us more to leverage the experience.

Team is allocating time to get on call and brainstorm on the UX designs.

STC

STC(+1)

Talks about PlayWright and enhancing locators

STC

STC(+2)

Start on Playwright (+12)Implemented JWT

Fruitful Discussion on Playwright

Team is back Back (+12)

S.No

Action Items

Assigned To

1.

Need action item to understand performance issue w Farhan, and create ticket+actions to resolve.

Abdul

OTP : Solution changed half-way through CTRL-ALT-K, and don’t have environment to verify → using farhan’s system for development, testing, both

See if we can use the other windows server 2019 to use it

Abdul

3

Have another person, participate in calls for status, record issues, update issue status; (Maroof)

Maroof

4

Write helper scripts for deployments to download and deploy the build. Ask Ahmer to work on this.

Ahmer

5

Create a script to create a build and publish to build, include build version number.

Abdul/Yassir

6

Change timing of scrum to accommodate STC schedule

Naveed

7

Need meetings with people for UX feedback to Sudharsan

Naveed